EDF Renewable Energy Confirms Turbine Order with Vestas for 220 Megawatts

published: 2013-12-23 13:24

EDF Renewable Energy has placed a firm order with Vestas for 220 megawatts (MW) of V100-2.0 MW wind turbine generators. The order is part of the Master Supply Agreement (MSA) announced in September 2013.

The most recent order brings the firm commitment of the Vestas turbines to 300 MW to meet the demands of two projects being constructed in the Texas Panhandle: Hereford 1 and Longhorn North. Deliveries and commissioning of both projects are expected to occur in the second half of 2014.

"We are pleased to be working with Vestas to bring additional Texas wind projects online over the next 18 months," said Ryan Pfaff, Executive Vice President at EDF Renewably Energy. "The Hereford 1 and Longhorn North projects will not only provide affordable, clean energy to the Texas grid, but also provide an economic boost to the local communities surrounding the projects, in the form of new jobs, local taxes, and other direct and indirect benefits."

EDF Renewable Energy’s U.S. portfolio spans 16 states with over 4,000 MW of developed projects and an installed capacity of 1,863 MW of wind, solar, biogas and biomass projects.
 